Shuttered Hospital transformed into Covid-19 Alternate Care Facility

Clark Construction Group collaborated with the U.S. Army Corps of Engineers to successfully transform a shuttered hospital south of Chicago, the MetroSouth Medical Center, into an Alternate Care Facility (ACF) to treat Covid-19 patients. The ACF will provide 585 surge beds, including 265 high acuity beds, to support critically ill patients. The joint venture helped deliver the project in just 22 days.

For more than a century, the MetroSouth Medical Center served the Blue Island community before closing in late 2019. A design-build team was led by Clark. The team had revitalized the once dormant facility into a fully operational ACF. They converted spaces like the emergency department, labor, and delivery, as well as hospital office space, into patient bed areas. The team also turned existing patient rooms with negative pressure units to meet air change and infection control requirements, as well as reactivated medical gas systems to support patients who require ventilators.

They also ensured that all 26 essential hospital systems were inspected, repaired, or replaced, and fully operational. The MetroSouth ACF project team also includes architect Perkins and Will, MEP engineer Salas O’Brien, as well as Hill Mechanical, Titan Electric, RG Construction, and Consolidated Flooring.

About three dozen personnel, along with design partners and more than 200 craftworkers, worked day and night to meet the ambitious timeline, according to Clark’s statement. Clark and his team, despite the challenging schedule, managed to maintain the safety protocols of the pandemic. Clark had received a Certificate of Occupancy on April 21, four days ahead of schedule. The state officials received the project on April 23.

The collaboration on site has been like nothing I have seen in 26 years of military service,” said Col. Aaron W. Reisinger, U.S. Army Corps of Engineers, Chicago District. “Everyone worked hand-in-hand to overcome challenges that otherwise would have taken weeks, if not months, to solve. This project brought out the best of humanity at all levels.”

Lucas Durden

Guest Writer

Recent Posts

High fuel costs may reshape American Airlines plans

American Airlines could reconsider its future capacity plans if elevated fuel prices persist, CEO Robert Isom said, even as strong…

2 days ago

Amazon Prime refunds expanded to as much as $200

More Amazon Prime customers will qualify for automatic refunds under a revised settlement with the Federal Trade Commission, with the…

3 days ago

Brandon Johnson Launches Chicago Reelection Bid

Chicago Mayor Brandon Johnson announced Sept. 15 that he will seek a second term, launching a reelection campaign centered on…

7 days ago

Phillies begin crucial playoff push vs. Nationals

The Philadelphia Phillies begin a crucial stretch in their postseason race Tuesday when they visit the Washington Nationals for the…

1 week ago

Chicago Fed Focuses on Banking and Housing

The Federal Reserve Bank of Chicago is focusing on two major economic issues this September, with events addressing the challenges…

1 week ago

Aaron Judge returns as Yankees beat Rockies

Aaron Judge returned to the New York Yankees lineup Tuesday after a lengthy absence, and while the three-time MVP had…

2 weeks ago

This website uses cookies.