Sullivan High School in Rogers Park. At 6631 N. Bosworth Ave. will underway massive renovations as Chicago has issued an $18 million building permit. The overall renovation cost for the school at 6631 N. Bosworth Ave. was estimated at $25 million, according to Block Club Chicago’s earlier reports.
Some of the renovation work includes replacing a leaky roof, overhauling the science labs and gymnasium, and other work, including installing new windows and masonry work to repair historic facade features. The gym will receive a new scoreboard, backboards, and bleachers. The science labs are also being upgraded.
The permit also references ADA upgrades, fire alarm upgrades throughout, interior hazardous material abatement, interior patching and painting, structural repairs, and deck infills, with associated mechanical, electrical, and plumbing work. Tyler Lane Construction Inc. is overseeing the project as a general contractor.
Key subtrades include: Electrical – Broadway Electric, Inc.; masonry – Illinois Window & Glass; plumber/plumbing – Caldwell Plumbing, Co., Inc.; and refrigeration and ventilation – May-Aire Heating and Cooling.
Chicago Mayor Brandon Johnson’s trip to Rome to visit the Pope is drawing renewed attention to ongoing public safety concerns…
The Milwaukee Brewers will have an opportunity to climb into first place in the National League Central when they continue…
Chicago Public Schools has lost nearly one-fifth of its student population over the past decade, even as the Chicago Teachers…
An Indian student was killed, and several others were injured, following a late-night two-vehicle crash near Chicago, according to Indiana…
Boeing could secure its largest Chinese aircraft deal in years after U.S. President Donald Trump announced that China plans to…
Chicago Fire FC announced Thursday that its Nov. 7 home match against the Columbus Crew will be relocated from Soldier…
This website uses cookies.